A general view of the fixing of the wall panels from floors 3 to 6 is shown. The raising
of the panels to floors 7 and 8 was undertaken by a single track monorail trolley tra-
versing the building at floor 8. It was further used for floors 9 to 15 at the rear of the
building frame.
Handling of external curtain wall panels
The handling methods of the external curtain wall panels are as follows:
Hydraulic tracked mini crane located two to four floors above the fixing level.
Wall panels on raised trolley platform, raised to appropriate floor level via internal
materials lift.
One fixing gang on hydraulic lifters at bottom edge of panel. Two handlers posi-
tioned at head of panel.
Curtain wall panel in position