Position pre-cast coffered units between steelwork to floors 3,4 & 5
Sequence Three: steelwork and floors 6
th
, 7
th
and 8
th
floor
The steelwork and precast coffered floors were erected over a 6 week period (June/July
2011). Work commenced to the services fit out to the lower ground floors