Type A work packages which fall into this category include:
●
Precast concrete coffered floor slabs.
●
Precast stairs and landings.
●
Curtain walling.
●
Precast wall panels and stone cladding.
●
Main safes.
●
Window cleaning cables.
●
Lifts.
An example of design responsibility for the precast concrete coffered floor slabs is
indicated both for the design consultants and the specialist subcontractors.
Precast coffered floor slabs - Design consultants responsibility
●
General arrangement drawings and sections.
●
Edge condition drawings.
●
Loading requirements.
●
Finishing specification.
●
Setting out.
●
Mix design specification.
●
Overall performance of floor.
Precast coffered floor slabs - Specialist subcontractor's responsibility
●
Mould design.
●
Reinforcement design and details.
●
Concrete mix design.
●
Structural design of precast floors.
●
Temporary propping and bracing system.
●
Lifting eyes.
Type B: consultants design with some subcontractor design
The design will be prepared by the design consultant, but elements of design tradi-
tionally prepared by specialist subcontractors, such as fixing details etc will be the
responsibility of the specialist subcontractor (and so on down to the final design
with other packages).
Type B work packages which fall into this category include:
●
CFA piling.
●
Excavation and earthworks (including retaining wall, basement and ground
floor slabs).
●
Structural steelwork and decking.
●
Concrete frame (staircase cores and structural toppings).
●
Secondary steelwork.
●
Roller shutter and metal doors.
●
Architectural and miscellaneous metalwork.
●
Vanity units.