Element
Description of work
Duration
1. Foundations
Bullivant NRG dynamic compaction
system used to stabilise area.
Pad foundations and ground beams
constructed to form foundations to
frame.
1 week NRG
3 weeks Fdts
2. Erect steel frame
Five-storey steel frame erected plus
plant room on part of roof area.
6w. steel frame
4w. fix metal
deck
3. Internal floors
Holorib metal deck floors fixed to
steelwork.
Access formed via precast concrete
stairs installed with frame erection.
Metal deck
4w. concrete
5 floors
150 mm in-situ concrete slab cast on
metal deck.
Concrete
4. Plant room
Erect steelwork to plant room.
1 week
5. External roof
(building
watertight)
150mm insulation fixed on top of
in-situ slab, laid to falls.
Tr ocal single layer finish.
1 week
6. Curtain walling
Aluminium curtain wall framework
fitted to three elevations of building.
Rear wall in rainscreen cladding.
14 weeks
7. Building services
and internal
partioning
Installation of building services/
internal partitioning on each floor
level with block walls around
staircase and lift areas.
29 weeks
16 weeks
8. External works
Paving around buildings and
construction of 40-bay car parking
facility.
Programme assessment sheet