Planning sheet
Ground floor to roof level
pre-cast crosswall frame
Hotel project
Operation
Dur Days
10
10
20
30
40
50
60
70
80
90
100
0
Mobilisation
10
10
40
Tr ansfer floor
30
40
49
Floor 1
9
49
58
Floor 2
9
58
67
Floor 3
9
Completion
67 74
94 days
Floor 4
7
74 81
Floor 5
7
81 88
Floor 6
7
88 94
Dismantle crane
6
Complete frame erection
(88-10)=78 days
Frame completion Programme 78 days
Overall programme 94 days
Hotel project planning sheet
 