8.10 Hotel block - sequence of work for floors 5 to 7
High level floor
Low
level
floor
Low level and high level floors
Sequence of work per floor
Low-level floor: - 9 days per floor
High-level floor: - 7 days per floor
Precast wall and floor sequence
May
Operation
Dur.
2345678910
11
12
13
14
15
16
17
18
19
4th floor
4th floor
complete
Erect walls
5 days
Erect floor
2 days
5th floor
complete
5th floor
Erect walls
5 days
Erect floor
2 days
Programme for high-level floor
 