RSR (Resource Selection Rule) is to select operation to be loaded in which
resource of resource group.
(1) Early ending time: select resource first used to finish operation
(2) Early start time: select resource first used to start operation
(3) Latest ending time: select resource last used to finish operation
(4) Same to previous operation: select resource used in previous operation
(5) No-bottleneck early start time: select resource no-bottleneck first used to start
operation
Relevant selection rule refers to when an operation selection rule is selected ,
then corresponding resource selection rules are automatically selected.
(1) Serial circulation order: select operation with the same or the next
maximum(minimum) serial value. When there is no operation with maximum
serial value, the order will be opposite and select the minimum operation.
(2) Serial decreasing order: select operation with the same or the next minimum
serial value
(3) Serial increasing order: select operation with the same or the next maximum
serial value
(4) Minimum preparing series: select operation with minimum preparing time
and recent serial value
(5) Minimum preparing time: select operation with minimum preparing or
changing time
(6) Serial circulation order of time zone: select operation with the same or the
next maximum(minimum) serial value. And only consider the operation of
the order finished date in the particular time zone. When there is no operation
with maximum serial value, the order will be opposite and select the
minimum operation.
(7) Serial decreasing order of time zone: select operation with the same or the
next minimum serial value . And only consider the operation of the order
finished date in the particular time zone.
(8) Serial increasing order of time zone: select operation with the same or the
next maximum serial value. And only consider the operation of the order
finished date in the particular time zone.
(9) Minimum preparing series of time zone: select operation with minimum
preparing time and recent serial value. And only consider the operation of the
order finished date in the particular time zone.