4.26
.4
.1
the execution of work not forming part of the Main Contract by the
Employer himself or by persons employed or otherwise engaged by
the Employer as referred to in clause 29 of the Main Contract
Conditions or the failure to execute such work;
4.26
.4
.2
the supply by the Employer of materials and goods which the
Employer has agreed to provide for the Works or the failure so to
supply;
4.26
.5 Architect's instructions under clause 23.2 of the Main Contract
Conditions issued in regard to the postponement of any work to be
executed under the provisions of the Main Contract which shall
be deemed to include Contractor's directions which pass on such in-
structions;
4.26
.6
failure of the Employer to give in due time ingress to or egress from the
site of the Works, or any part thereof through or over any land, build-
ings, way or passage adjoining or connected with the site and in the
possession and control of the Employer, in accordance with the Contract
Bills/Specification/Schedules of Work and/or the Contract drawings,
after receipt by the Architect of such notice, if any, as the Contractor is
required to give or failure of the Employer to give such ingress or egress
as otherwise agreed between the Architect and the Contractor;
4.26
.7 Architect's instructions issued:
under clause 13.2 or clause 13A.4.1 of the Main Contract Conditions
requiring a Variation (except for a Variation for which the Architect has
given a confirmed acceptance of a 13A Quotation or for a Variation
thereto) or under clause 13.3 of the Main Contract Conditions in regard
to the expenditure of provisional sums (other than work to which clause
13.4.2 of the Main Contract Conditions refers or an instruction for the
expenditure of a provisional sum for defined work or of a provisional
sum for Performance specified Work);
which shall be deemed to include Contractor's directions which pass on
such instructions.
4.26
.8 .1
the execution of work for which an Approximate Quantity is in-
cluded in the Contract Bills which is not a reasonably accurate
forecast of the quantity of work required;
4.26
.8 .2 where bills of quantities are included in the Numbered Documents
the execution of work for which an Approximate Quantity is
included in those bills which is not a reasonably accurate forecast
of the quantity of work required;
4.26
.9
compliance or non-compliance by the Employer with clause 6A.1 of the
Main Contract Conditions;
4.26
.10 .1 suspension by the Contractor of the performance of his obligations
under the main Contract to the Employer pursuant to clause 30.1.4 of
the main Contract conditions provided the suspension was not
frivolous or vexatious;