except to the extent that the failure referred to in clause 2.6.6.1 or clause 2.6.6.2
results from a breach by the Sub-Contractor of his obligations to the Employer
under clause 3.2 of Agreement NSC/W.
2.6
.7 delay on the part of nominated sub-contractors (other than the Sub-
Contractor) or of nominated suppliers in respect of the Works which
the Contractor has taken all practicable steps to avoid or reduce;
2.6
.8
.1
the execution of work not forming part of the Main Contract by the
Employer himself or by persons employed or otherwise engaged by
the Employer as referred to in clause 29 of the Main Contract Condi-
tions or the failure to execute such work;
2.6
.8
.2
the supply by the Employer of materials and goods which the Em-
ployer has agreed to provide for the Works or the failure so to supply;
2.6
.9
the exercise after the Base Date by the United Kingdom Government of
any statutory power which directly affects the execution of the Works by
restricting the availability or use of labour which is essential to the proper
carrying out of the Works, or preventing the Contractor or Sub-Con-
tractor from, or delaying the Contractor or Sub-Contractor in, securing
such goods or materials or such fuel or energy as are essential to the
proper carrying out of the Works;
2.6
.10
.1
the Contractor's or Sub-Contractor's inability for reasons beyond his
control and which he could not reasonably have foreseen at the Base
Date for the purposes of the Main Contract or the Sub-Contract as
the case may be to secure such labour as is essential to the proper
carrying out of the Works; or
2.6
.10
.2
the Contractor's or Sub-Contractor's inability for reasons beyond his
control and which he could not reasonably have foreseen at the Base
Date for the purposes of the Main Contract or the Sub-Contract as
the case may be to secure such goods or materials as are essential to
the proper carrying out of the Works:
2.6
.11
the carrying out by a local authority or statutory undertaker of work in
pursuance of its statutory obligations in relation to the Works, or the
failure to carry out such work;
2.6
.12
failure of the Employer to give in due time ingress to or egress from the
site of the Works or any part thereof through or over any land, build-
ings, way or passage adjoining or connected with the site and in the
possession and control of the Employer, in accordance with the Contract
Bills and/or Contract Drawings and/or Specification/Schedules of
Work and/or Numbered Documents, after receipt by the Architect of
such notice, if any, as the Contractor is required to give, or failure of the
Employer to give such ingress or egress as otherwise agreed between
the Architect and the Contractor;
2.6
.13 delay arising from
2.6
.13
.1
a suspension by the Contractor of the performance of his obligations
under the Main Contract to the Employer pursuant to clause 30.1.4
of the main Contract Conditions; and/or