. a change made in order to accept a Defect or
. a change to the Works Information provided by the Contractor for
his design which is made at his request or to comply with other
Works Information provided by the Employer .
(2) The Employer does not give possession of a part of the Site by the later of
its possession date and the date required by the Accepted Programme.
(3) The Employer does not provide something which he is to provide by
the date for providing it required by the Accepted Programme.
(4) The Project Manager gives an instruction to stop or not to start anywork.
(5) The Employer or Others do not work within the times shown on the
Accepted Programme or do not work within the conditions stated in
the Works Information.
(6) The Project Manager or the Supervisor does not reply to a communi-
cation from the Contractor within the period required by this contract.
(7) The Project Manager gives an instruction for dealing with an object of
value or of historical or other interest found within the Site.
(8) The Project Manager or the Supervisor changes a decision which he has
previously communicated to the Contractor .
(9) The Project Manager withholds an acceptance (other than acceptance
of a quotation for acceleration or for not correcting a defect).
(10) The Supervisor instructs the Contractor to search and no Defect is found
unless the search is needed only because the Contractor gave insuffi-
cient notice of doing work obstructing a required test or inspection.
(11) A test or inspection done by the Supervisor causes unnecessary delay.
(12) The Contractor encounters physical conditions which
. are within the Site,
. are not weather conditions
. an experienced contractor would have judged at the Completion
Date to have such a small chance of occurring that it would have
been unreasonable for him to have allowed for them.
(13) A weather measurement is recorded
. within a calendar month,
. before the Completion Date for the whole of the works and
. at the place stated in the Contract Data
the value of which, by comparison with the weather data , is shown to occur
on average less frequently than once in ten years.
(14) An Employer' s risk event occurs.
(15) The Project Manager certifies takeover of a part of the works before both
Completion and the Completion Date.
(16) The Employer does not provide materials, facilities and samples for
tests as stated in the Works Information.
(17) The Project Manager notifies a correction to an assumption about the
nature of a compensation event.
(18) A breach of contract by the Employer which is not one of the other
compensation events in this contract.
60.2 In judging the physical conditions, the Contractor is assumed to have taken
into account