. a change made in order to accept a Defect or
. a change to the Works Information provided by the
Contractor
for
his design which is made at his request or to comply with other
Works Information provided by the
Employer
.
(2) The
Employer
does not give possession of a part of the Site by the later of
its
possession date
and the date required by the Accepted Programme.
(3) The
Employer
does not provide something which he is to provide by
the date for providing it required by the Accepted Programme.
(4) The
Project Manager
gives an instruction to stop or not to start anywork.
(5) The
Employer
or Others do not work within the times shown on the
Accepted Programme or do not work within the conditions stated in
the Works Information.
(6) The
Project Manager
or the
Supervisor
does not reply to a communi-
cation from the
Contractor
within the period required by this contract.
(7) The
Project Manager
gives an instruction for dealing with an object of
value or of historical or other interest found within the Site.
(8) The
Project Manager
or the
Supervisor
changes a decision which he has
previously communicated to the
Contractor
.
(9) The
Project Manager
withholds an acceptance (other than acceptance
of a quotation for acceleration or for not correcting a defect).
(10) The
Supervisor
instructs the
Contractor
to search and no Defect is found
unless the search is needed only because the
Contractor
gave insuffi-
cient notice of doing work obstructing a required test or inspection.
(11) A test or inspection done by the
Supervisor
causes unnecessary delay.
(12) The
Contractor
encounters physical conditions which
. are within the Site,
. are not weather conditions
. an experienced contractor would have judged at the Completion
Date to have such a small chance of occurring that it would have
been unreasonable for him to have allowed for them.
(13) A
weather measurement
is recorded
. within a calendar month,
. before the Completion Date for the whole of the
works
and
. at the place stated in the Contract Data
the value of which, by comparison with the
weather data
, is shown to occur
on average less frequently than once in ten years.
(14) An
Employer'
s risk event occurs.
(15) The
Project Manager
certifies takeover of a part of the
works
before both
Completion and the Completion Date.
(16) The
Employer
does not provide materials, facilities and samples for
tests as stated in the Works Information.
(17) The
Project Manager
notifies a correction to an assumption about the
nature of a compensation event.
(18) A breach of contract by the
Employer
which is not one of the other
compensation events in this contract.
60.2 In judging the physical conditions, the
Contractor
is assumed to have taken
into account