tion of the Works in respect of a Variation for which a 13A Quotation
has been given and which has been stated in a confirmed acceptance of
a 13A Quotation or in respect of a Variation or work for which an
adjustment to the time for completion of the Works has been accepted
pursuant to clause 13.4.1.2 paragraph A7.
25.3
.3 After the Completion Date, if this occurs before the date of Practical
Completion, the Architect may, and not later than the expiry of 12 weeks
after the date of Practical Completion shall, in writing to the Contractor
either
25.3
.3
.1
fix a Completion Date later than that previously fixed if in his
opinion the fixing of such later Completion Date is fair and reason-
able having regard to any of the Relevant Events, whether upon
reviewing a previous decision or otherwise and whether or not the
Relevant Event has been specifically notified by the Contractor
under clause 25.2.1.1; or
25.3
.3
.2
fix a Completion Date earlier than that previously fixed
under clause 25 or stated in a confirmed acceptance of a 13A Quota-
tion if in his opinion the fixing of such earlier Completion Date is fair
and reasonable having regard to any instructions issued after the last
occasion on which the Architect fixed a new Completion Date
— under clause 13.2 which require or sanction as a Variation the
omission of any work or obligation; and/or
— under clause 13.3 in regard to the expenditure of a provisional
sum for defined work or for Performance Specified Work
which result in the omission of any such work; or
25.3
.3
.3
confirm to the Contractor the Completion Date previously fixed or
stated in a confirmed acceptance of a 13A Quotation.
25.3
.4 Provided always that:
25.3
.4
.1
the Contractor shall use constantly his best endeavours to prevent
delay in the progress of the Works, howsoever caused, and to
prevent the completion of the Works being delayed or further
delayed beyond the Completion Date;
25.3
.4
.2
the Contractor shall do all that may reasonably be required to the
satisfaction of the Architect to proceed with the Works.
25.3
.5 The Architect shall notify in writing to every Nominated Sub-Contractor
each decision of the Architect under clause 25.3 fixing a Completion
Date and each revised Completion Date stated in the confirmed accept-
ance of a 13A Quotation together with, where relevant, any revised
period or periods for the completion of the work of each Nominated
Sub-Contractor stated in such confirmed acceptance.
25.3
.6 No decision of the Architect under clause 25.3.2 or clause 25.3.3.2 shall
fix a Completion Date earlier than the Date for Completion stated in the
Appendix.
25.4 The following are the Relevant Events referred to in clause 25: