Environmental Engineering Reference
In-Depth Information
Figure B-25 Porous pavement was used only in parking bays.
Granite cubing
Granite band
Access arsle
Granite cubing
Parking bay
Parking bay
Porous
asphalt paving
Porous asphalt paving
Impervious
asphalt paving
Filter fabric
Recharge bed
Compacted
subgrade
Uncompacted subgrade
Compacted
subgrade
5
4
Section through parking lot and stormwater recharge bed
3
1
2
Figure B-26 Section through pavements and stone infiltration bed.
Campus Master Plan, DuPont Barley Mills Office Center,
New Castle County, DE (1985)
Cahill Associates and Andropogon Associates were retained by DuPont to
develop a sustainable plan for a new office complex that would serve a number
of company subsidiaries, including the worldwide headquarters for agricultural
chemicals. The land development program was under way when they were
retained, but they were able to design a new parking lot system for this part of
the site, using porous AC over a stone recharge bed, and including the rooftop
Search WWH ::