Civil Engineering Reference
In-Depth Information
The caisson - a closed concrete box structure which is provided with a cen-
tral wall - has a width of 34.60 metres, a length of 25 metres and a height of
24.10 metres. An open basin structure with a width of 29 metres and a length
of 260.50 metres connects onto the receiving shaft. This basin is carried out
in 15 sections with expansion joints with a length varying from 10 metres to
20 metres. The basin structure is built in a construction pit within anchored
sheet pile walls. At the 10 deepest sections, the bottom sealing consists of a
floor made of underwater concrete. At the remaining sections within the sheet
piling, drainage was applied in which use was made of a poorly permeable,
sand-containing clay stratum at approximately 7 to 9 metres
NAP.
The entire access ramp is surrounded by a surrounding dyke with a construc-
tion height of 6.50 metres
NAP.
Fig. 8.7
Design access ramp
north
25 m
43 m
160 m
Open basin
Closed exit
open entrance
Infill
Impermeable block
Caisson
6.50 m
2.50 m
Tensile piles
Sheet piling
20.70 m
Diaphragm wall
Adapting the building of the caisson - first phase
Initially the idea was that the caisson could be built at the surface level. To
this end, the soft covering layer (clay and peat) - present down to approxi-
mately 4.50 metres below the surface - had to be replaced by a ground
improvement consisting of sand. As a result of the higher rising height
in the aquiferous layers under this pack (in the construction phase up to
1 metre
NAP, and thus approximately 1.50 metres above the existing sur-
face), the building of the caisson could not have been realised without
drainage or an enclosing dyke. That is why the choice was eventually made
for the construction of a construction pit in which the soft deposits could be
excavated. By making use of a water-braking layer situated approximately
8 metres
NAP the drainage remained extremely limited. Due to this the
construction level of the caisson was also reduced by approximately 4
metres. After casting the floor of the caisson, the construction pit could be
removed.
As opposed to the receiving shaft of the access ramp south, the walls of the
caisson with a height of 16.60 metres were cast in 4 layers. An active cooling
of each casting was necessary in order to achieve a crack-free and thus
waterproof structure.The following facilities were applied for the immersion
of the caisson:
- the usual immersion facilities such as:
a cutting edge and excavation chamber for the excavation under
increased air pressure;
air locks for personnel and equipment in order to gain access to the
excavation chamber;
bentonite piping located at the external walls for the reduction of the
soil friction;
Search WWH ::




Custom Search