Civil Engineering Reference
In-Depth Information
f c -1.72σ
1.28
1 - σ 2 )
f c
( k = 1.28)
f +1.28σ 2
2 = 2.5)
f +1.28σ 1
1 = 5.0)
(3σ 2 - σ 2 )
f c - 5
( k = 3)
f c - 5
+3σ 2
2 = 2.5)
f c - 5
+3σ 1
1 = 5.0)
Figure 11.2 Effect of compensated increase in k is to improve competitive position of
low-variability supplier and rule out low results from high-variability supplier.
but could be applied with mutual agreement in practice. The effect of ana-
lysing 30 results overlapping a change point is to give an artificially inflated
standard deviation, which is only slightly compensated for by the increased
mean strength obtained from the inclusion of a few higher results and,
therefore, causes a higher penalty. An alternative, slightly lower penalty
based on the actual defective period can be offered, but the specification
can be strictly enforced without substantial unfairness.
Figure  11.3 shows a run of understrength results that merit a penalty.
Under the proposed specification, the lowest 30-result section (representing
600 m 3 [785 yd 3 ] of concrete) must form the basis. 1 A penalty of $6.16 m 3
would be applied, totaling $3696.
Close analysis, however, reveals that the low strength concrete is con-
fined to a 20-result section (representing 400 m 3 [523 yd 3 ] of concrete). 2
The penalty/m 3 based on the 20 results would be greater but the overall
penalty would be less at $7.67 × 400 = $3068. The latter penalty is the
more equitable and is the one that should actually be imposed. However,
1 The average strength over the thirty results in 31.56 MPa (or 2.28 MPa less than the target
of 33.84 MPa based on a SD of 3 MPa and K = 1.28).
2 The average strength over the twenty results is 31 MPa (or 2.84 MPa less than the target).
 
Search WWH ::




Custom Search