Table 9.3 Example of a calendar of activities in afforestation project
Sr. No.
Activity
Time
Result/Product of activity
Who to do
Starting date
Ending date
Period (days)
1
Selecting site, getting it approved and surveying it
15-Sep
15-Oct
31
Site map
UM
2
Preparation of treatment plan after thorough
inspection of site
16-Oct
30-Oct
15
Draft treatment plan
UM
3
Examining treatment plan proposed by UM and
approving it
1-Nov
15-Nov
15
Treatment plan
DM
4
Preparation of detailed estimates and submission in
divisional office
16-Nov
30-Nov
15
Proposed estimates
UM
5
Approval of detailed estimates
1-Dec
15-Dec
15
Estimates
DM
6
Execution of the fencing work at site
16-Dec
15-Feb
61
Fenced area
SR
7
Marking contour lines in filed with lime, inspection of
the same by UM and approval
30-Dec
30-Jan
31
S&WC works marked
SR, UM
8
Inspection & approval of contour alignment of S&WC
works by DM
1-Feb
15-Feb
15
S&WC plan approved
DM
9
Execution of S&WC works in field
16-Feb
16-May
91
S&WC structures
SR
10
Setting up of nursery or readying permanent nursery
for raising of plants
15-Oct
30-Oct
16
Nursery ready for plant prod.
SR
11
Procurement of seeds, polypots, pesticides etc.
15-Sep
15-Dec
92
Seeds, poly-pots, avail.
DM
12
Procurement of clay, manure etc.
1-Oct
1-Nov
32
Potting mix available
UM
13
Filling of polypots with potting mix
16-Dec
16-Jan
31
Polypots in beds
SR
14
Sowing of seeds of xerophytic species/other species of
late season, including resowing
16-Jan
28-Feb
44
Germination of seeds starts
SR
15
Submission of advance action completion statement
15-May
20-May
6
Advance action completion
UM
by the UM of all sites
report is available
DM Divisional manager, SR Supervisor, UM Unit manager
 