Table 7.13 Model treatment plan for regenerative closures (RC-600)
Sr. No.
Item/activity
Specifications of item
Quantity
Year of execution
1
Survey and demarcation
Surveying the area with chain and compass, demarcating it with
monoliths or masonry pillars, and preparation of map of the area
1:5,000 scale, topo-map and treatment maps
50 ha
Y1
2
Fencing
Fencing the area with dry-stone wall of section SW-1, with suitable
provision for drainage of water at required number of places
3,000 m
Y1
3
Soil and water conservation works
3.1 Digging of contour trench of section CT-1, at a spacing suitable
for terrain, say from 10 m to 20 m depending upon slope, in soils
of hardness class:
(a) S3
75,000 m
Y1
(b) S4
15,000 m
Y1
(c) S5
75,000 m
Y1
750 m 3
3.3 Construction of loose-stone check dams (LSCDs) across
streams, etc.
Y2
3.4 Construction of saucers of 1 m diameter around the naturally
growing seedlings, in order to harvest and retain water, in soils of
hardness class:
(a) S1, S2 or S3
1,000 nos.
Y2
(b) S4 or S5
500 nos.
Y2
4
Sowing of seeds for CVH, on keylines
4.1 Sowing of seeds of tree and shrub species in two parallel rows at
20 cm spacing on the bunds of contour trench, along fence, etc. by
hand dibbling, just before rains
66,000 row-m
Y2
4.2 Sowing of seeds in notches made in cracks, pockets of soil, etc.
seen in rocky and too steep areas
20,000 nos.
Y2
5
Aftercare and maintenance
5.1 Weeding operation in sowing on keylines 30 days after first rains
33,000 m
Y2, Y3, Y4
5.2 Second weeding operation in sowing on keylines 15 days after
the last rains of the season
33,000 m
Y2, Y3
100 m 3
5.3 Repair and maintenance of fence after the last rains, and
continuously as and when required
Y2, Y3, Y4, Y5
 