Table 7.4 Model treatment plan for rehabilitation of degraded forest (RDF-400)
Sr. No.
Item/activity
Specifications of item
Quantity
Year of execution
1
Survey and demarcation
Surveying the area with chain and compass, demarcating it with
monoliths or masonry pillars, and preparation of map of the area
1:5,000 scale, topo-map and treatment maps
50 ha
Y1
2
Fencing
Fencing the area with dry-stone wall of section SW-1, with suitable
provision for drainage of water at required number of places
3,000 m
Y1
3
Nursery work
Raising of plants in temporary nursery on site, including 20 % extra
plants for casualty in handling, transport etc.
24,000 nos.
Y1, Y2
4
Soil and water conservation works
4.1 Digging of contour trench of section CT-1, at spacing suitable for
terrain, say from 10 m to 20 m depending upon slope, in soils of
hardness class:
Y1
(a) S3
75,000 m
(b) S4
15,000 m
(c) S5
75,000 m
4.2 Excavation of pits of standard size P-3 in the space between the
contour lines, in soils of hardness class:
Y2
(a) S3
5,000 nos.
(b) S4
10,000 nos.
(c) S5
5,000 nos.
750 m 3
4.3 Construction of loose-stone check dams
Y2
4.4 Construction of saucers of 1 m diameter around the naturally growing
seedlings, in order to harvest and retain water, in soils of hardness class:
Y2
(a) S1, S2 or S3
1,000 nos.
(b) S4 or S5
500 nos.
4.5 Construction of saucers of 1 m diameter around the planted seedlings
or young plants, in order to harvest and retain water, in soils of
hardness class:
Y2
(a) S1, S2, or S3
5,000 nos.
(b) S4 or S5
15,000 nos.
5
Sowing of seeds for CVH, on
keylines
5.1 Sowing of seeds of tree and shrub species in two parallel rows at
20 cm spacing on the bunds of contour trench, along fence, etc. by
66,000 row-m
Y2
 