Table 7.1 (continued)
Sr. No.
Item specifications
Unit of work
Required man-days
Unskilled
Semi-skilled
Skilled
3-30
Inspection path
Preparation of motorable inspection path in plantation area, 3 m wide, where feasible,
including clearing of shrubs, levelling pits, and removal of large boulders etc., and marking
its borders with whitewashed stones lined at 1 m interval:
(a) In highly rugged or hilly terrain
1,000 m 2
22
1,000 m 2
(b) In rolling terrain with medium slopes
15
1,000 m 2
(c) In flat or slightly undulating terrain
8
Part-4: Soil and water conservation works
4-1
Excavation of contour trench on alignment marked in field, including forming of excavated
soil into a bund along the edge of the trench on the lower side according to ground slope:
(a) Trench being of standard section CT-1 (0.09 m 2 ), and the soil being of hardness class:
(i) S1
1,000 m
36
(ii) S2
1,000 m
40
(iii) S3
1,000 m
45
(iv) S4
1,000 m
60
(v) S5
1,000 m
90
(vi) S6
1,000 m
180
(b) Trench being of standard section CT-2 (0.1225 m 2 ), and the soil being of hardness class:
(i) S1
1,000 m
49
(ii) S2
1,000 m
54
(iii) S3
1,000 m
61
(iv) S4
1,000 m
82
(v) S5
1,000 m
122
(vi) S6
1,000 m
245
(c) Trench being of standard section CT-3 (0.2025 m 2 ), and the soil being of hardness class:
(i) S1
1,000 m
81
(ii) S2
1,000 m
90
(iii) S3
1,000 m
101
 