Information Technology Reference
In-Depth Information
If one person is assigned that task, then first he will do preparation for the task and
then he will start working on the task. Suppose preparation requires 8 hours and
the task requires 8 hours. If you assign two people for this task, then each person
will take 8 hours for preparation. The task may be divided and each person may
take 4 hours to complete his portion of the task. In the first case, it will take 16
hours (preparation time
+
task completion time). In the second case, it will take 12
hours if there is no dependency between the divided tasks. But if there is a depen-
dency, then the task completion will still take 16 hours, as the dependent task can-
not be started until the task on which this task depends completes.
So you see, even after adding resources, you cannot complete a task faster.
... Effort Estimation Checklist
4.8.1
Checklist for Software Test Schedule Estimation
◾
Have test life cycle stages been identified?
◾
Has size estimation for each phase been identified?
Have the activities for each phase been identified?
◾
◾
Has size estimation for the test case design phase been identified?
Has size estimation for the test requirement phase been identified?
◾
◾
Has size estimation for the test case execution phase been identified?
Has size estimation for the test script development phase been identified?
◾
◾
Have size and schedule estimations for the regression cycle been made?
Has schedule estimation for each phase been identified?
◾
◾
security, compatibility, integration, and any other type of testing) been done?
Has schedule estimation for all kinds of testing (functional, performance,
4.8.2
Checklist for Software Test Effort Estimation
◾
Have test life cycle stages been identified?
◾
Has size estimation for each phase been identified?
Have the activities for each phase been identified?
◾
◾
Has size estimation for the test case design phase been identified?
Has size estimation for the test requirement phase been identified?
◾
◾
Has size estimation for the test case execution phase been identified?
Has size estimation for the test script development phase been identified?
◾
◾
Have size and effort estimations for the regression cycle been made?
Has effort estimation for each phase been identified?
◾
◾
rity, compatibility, integration, and any other type of testing) been done?
Has effort estimation for all kinds of testing (functional, performance, secu-