Mixing team
Scenario: The supply of materials close to the mixer runs out, so more materials need to
be brought over (sometimes this might also require the mixer being disengaged from the
telehandler so that it can be used to transport materials).
Problem: If there is a delay in getting the next mix on, this might stop the whole operation
and leave the ferrying team and placing team with nothing to do.
Solution: People from the other teams are assigned to the mixing team, so that materials
can be brought up while mixing continues. If a telehandler is needed to move materials
and this will stop the mixer, a temporary solution is for the extra team members to move
(by hand) enough materials to keep the mixer going until the next scheduled break, when
the telehandler (and the whole build team) is used to replenish materials, since the placing
work has stopped anyway.
The person mixing must be kept supplied with binder and hemp.