Method 2 works better for shuttering on an exposed frame internally, where the boards
are fixed straight to the timbers without spacers on the internal side of the board. With
a central frame, Method 1 is the preferred option, as Method 2 can result in the corner
being repositioned in relation to the (floating) timber, rather than being fixed in relation
to the frame timbers as per the design.