Civil Engineering Reference
In-Depth Information
Hempcrete placed between rafters using 'lollipops'.
Once erected, each shuttering board should be checked with a straight edge to see that it
is in line with neighbouring boards. It should also be checked for plumb with a level, and
the distance between the inside face and frame should be double-checked at several places
along the top of the board.
When removing the shuttering once the hempcrete has taken its initial set, remember that,
until you reach the top of the wall, the top shuttering board - the one level with the top
of the hempcrete - has to remain in place while another board is fixed above it and filled.