Environmental Engineering Reference
In-Depth Information
• Average monthly quantity (kg/day)
• Average monthly concentration (mg/L)
• Average weekly quantity (kg/day)
• Average weekly concentration (mg/L)
• Average hourly concentration (mg/L)
Daily quantity (kg/day)
• Daily concentration (mg/L)
• Instantaneous minimum concentration (mg/L)
• Instantaneous maximum concentration (mg/L)
11.3.2 Compliance schedules
If the facility requires additional construction or other modifications
to fully comply with the final effluent limitations, the permit will contain
a schedule of events to be completed to achieve full compliance.
11.3.3 special Conditions
Any special requirements or conditions set for approval of the
discharge will be contained in this section. Special conditions may
include:
Monitoring required to determine effluent toxicity
Pretreatment program requirements
11.3.4 licensed operator requirements
The permit will specify, based on the treatment system complex-
ity and the volume of flow treated, the minimum license classification
required for someone to be the designated responsible charge operator.
11.3.5 Chlorination/dechlorination reporting
Several reporting systems apply to chlorination or chlorination fol-
lowed by dechlorination. It is best to review this section of the specific
permit for guidance. If confused, contact the appropriate state regula-
tory agency.
11.3.6 reporting Calculations
Failure to accurately calculate report data will result in violations
of the permit. The basic calculations associated with completing the
DMR are covered below.