Database Reference
In-Depth Information
Figure 5-31. Create Consolidation Project screen
This screen is full of information needed to define a consolidation project. The first item that has to be decided
is the type of consolidation that is going to be done. The two options are Physical to Oracle Virtual Machine (P2V)
and Physical to Physical (P2P). Next, we have to choose what servers are going to be involved in the consolidation.
When adding a target for consolidation, first we have to add a source server. We also have the option of adding
existing virtual servers as destinations if needed. After the source target or OVM destination is added, you'll see a lot of
estimates that are specific to that source or destination server (see Figure 5-32 ).
Figure 5-32. Source server added for consolidation
 
Search WWH ::