The owner of the project discussed in example 4.3 needs to have the project
finished in 30 days. Use the imposed finish date to determine the effect on
the entire schedule and on individual activities. See Figure 4.15.
Figure 4.15 Effect of imposed finish date on the schedule
Solution
The results of example 4.7 can be tabulated as follows.
Activity
Duration
ES
EF
LS
LF
TF
A
2
0
2
5
3
5
B
7
2
9
3
10
1
C
10
2
12
37 5
D
4
2
6
3
7
1
E
6
9
15
16
22
7
F
5
12
17
10
15
2
G
8
12
20
7
15
5
H
9
6
15
12
21
6
I
12
20
32
15
27
5
J
5
17
22
17
22
0
K
5
22
27
22
27
0
L
6
20
26
21
27
1
M
4
17
21
23
27
6
N
3
32
35
27
30
5
 