advantage) but also did not make the logic as clear as it was in networks. This exper-
iment was followed, in the software industry, by adding enhanced options such as
“show only critical relationships” or “show only driving relationships.” In some simple
cases, this approach might work as a good and acceptable solution.
CHAPTER 3 EXERCISES
1.
What does a node mean in an arrow diagram?
2.
What does an arrow mean in an arrow diagram?
3.
What does a node mean in a node diagram?
4.
What does a line mean in a node diagram?
5.
What are the main differences between bar charts and networks?
6.
What are the differences between arrow and node networks?
7.
Arrow networks have another name; what is it? What is the reason for this
name?
8.
What are the main advantages of node networks over arrow networks?
9.
What is the main advantage of arrow networks over node networks? How was it
overcome?
10.
What are
time-scaled logic diagrams
? Discuss their practicality.
11.
What are the main advantages of networks over bar charts? How did bar charts
manage to stay popular despite the advantages of networks?
12.
Did logic networks and the critical path method replace bar charts as a scheduling
technique? Explain your answer.
13.
Draw both the arrow network and the node network for the following project:
Activity
IPA
A
-
B
A
C
A
D
B
E
B, C
14.
Draw both the arrow network and the node network for the following project:
Activity
IPA
A
-
B
-
C
A
D
A, B
E
C, D