Figure 3.21 Intersecting relationship lines in node networks
Figure 3.22a. The same concept applies to the end of the network: if it ends
with one activity, then there is no need for an additional node. If not (such
as those in Figures 3.11 to 3.15), then insert a PF (Project Finish) milestone
node at the end and tie those activities that end the network to it, as shown in
Figure 3.22b.
Tip Box 3.1
Every network must start with only one node and must finish with only one node.
A
A
B
PS
B
C
C
Improper Proper
(a) Do not start a network with more than one node
X
X
Y
Y
PS
Z
Z
Improper Proper
(b) Do not end a network with more than one node
Figure 3.22 Converging the start and finish of node networks