GRAPHIC REPORTS
Report 6:
Report 6 (Figure B.1) is a bar (Gantt) chart that shows the original dura-
tion, early dates, late dates, and total float in the tabular section. The bar chart shows
the float bar. The user may opt to hide it. The report is grouped by primary code
(phase) and secondary code (department).
Report 7:
Similar to report 6, report 7 (Figure B.2) has an addition and a deletion.
We added the remaining duration and percent complete (since the project has already
started), and omitted the late dates and total float. We also hid the float bar in the bar
chart section. In both reports 6 and 7, relationship lines may be displayed in the bar
chart section.
Report 8:
Report 8 (Figure B.3) is a logic diagram grouped by phase. Note that
completed activities are shown as boxes with two diagonal lines. Boxes representing
in-progress activities are designated with one diagonal line. Activities that have not
started do not have diagonal lines.
Report 9:
Report 9 (Figure B.4) looks like a tabular report, since the bar chart
was hidden. The report shows activity status and budget information.
Report 10:
Similarly to report 9, report 10 (Figure B.5) shows a bar chart. Such
a report should be printed on wider paper or the font size will be too small.
Report 11:
Report 11 (Figure B.6) is a bar chart that contains a resource usage
profile.