Civil Engineering Reference
In-Depth Information
Example 3.2
Draw the arrow network for the project given next.
Activity
IPA
A
-
B
A
C
A
D
B, C
Solution A
The main problem in this case, as shown in Figure 3.2, is that both activities
B and C start from node 20 and finish at node 30. Hence, both are identified
as 20-30.
This situation will create an identity problem. To solve this problem, we
introduce a fictitious activity and an additional node. This fictitious activity is
called a dummy activity , d. It is treated in the critical path method (CPM)
calculations (discussed in Chapter 4) and in computer programs as a real
activity even though it is not.
Figure 3.2a Improper solution for example 3.2
Solution B
In this case, activity B is identified as 20-30, whereas activity C is 20-40,
as shown in Figure 3.3. Note that the dummy can be inserted in different
positions, as shown next. They all serve the same purpose.
Figure 3.2b Proper solution for example 3.2
 
Search WWH ::




Custom Search