Project Update and Solution
1. Using traditional CPM relationships, we calculate the regular early and
late dates for both activities at day 0, that is, before any work occurs.
2. By day 10 (end of day 10), assume only 40% of activity A (Roof Sheath-
ing) is completed.
Activity A : Started on time: end of day 0, that is, beginning of day 1
Actual duration = 10 days
Remaining duration = 10 days ( productivity will pick up in the last
10 days )
At completion duration = 20 days
Activity B : Started end of day 3, that is, 2 days earlier than scheduled
Actual duration = 7days
Remaining duration = 11 days ( assuming the end of activity A + 1day )
Using the DML equation:
AD B ( 1 PC A )+ L
PC A
RD B
RD B
[ 7 ( 1 0 . 40 )+ 1 ]∕ 0 . 40 = 13 days
Finish date for Activity B
day 23, not day 21 as calculated by the
FF relationship.
3. Day 15: Assume only 70% of activity A (Roof Sheathing) is completed:
Activity A:
Actual duration = 15 days
Remaining duration = 5days
At completion duration = 20 days
Activity B:
Actual duration = 12 days
Remaining duration = 6days ( Assuming the end of activity A + 1day )
 