SIMILARITY BETWEEN THE DML CONCEPT AND THE LINEAR
SCHEDULING METHOD (LSM)
The DML relationship is similar to the LSMmethod
2
in maintaining a distance or time
buffer (see Figure 12.2a), but they are not the same. There are two main differences:
1.
LSM is a different scheduling method from CPM and cannot be implemented
in network scheduling or use CPM calculations. DML is just a logic relation-
ship that is fully compatible with CPM calculations and network scheduling.
Minimum lag
A
B
Time
(a)
5
0,10
A
10
5,11
B
6
(b)
1
0,10
5,11
A
10
B
6
(c)
1
0,10
5,11
A
10
B
6
1
(d)
Figure 12.2 Two overlapping activities represented in LSM graph and three different
PDM networks (SS, FF, and SS
+
FF), all leading to the same dates. Activities are
assumed to be contiguous.
2
Refer to the linear scheduling method (LSM) discussed in Chapter 11.