Civil Engineering Reference
In-Depth Information
Figure 11.13 The linear scheduling method (LSM)
Figure 11.14 Time and distance buffers in the LSM
Consider, for example, a carpentry crew that is installing and taping drywall for
a total of 10,000 square feet (SF). The production rate for the crew is 500 SF per
day for installation and taping. The painting crew is directly behind, at a production
rate of 800 SF per day. Assume that the painting crew starts on day 2 (1 day after
the carpentry crew started); then, at the end of day 3, the carpentry crew would have
finished 500
3 = 1,500 SF, but the painting crew would have finished 800
2 =
1,600 SF, which is impossible. There are four solutions for this problem.
1. Speed up the rate of the carpentry crew.
2. Slow the rate of the painting crew.
Search WWH ::




Custom Search