Civil Engineering Reference
In-Depth Information
The pessimistic duration is the duration under the worst-case scenario. Both values
must be within the realistic, although perhaps unlikely, realm of expectations.
The mean-weighted value for these three durations is called the expected dura-
tion ( T e ). It is calculated as follows:
T o + 4 T m + T p
6
T e =
(11.1)
and T p ) may be
adjusted, but the denominator must equal the sum of all of the weights. The weights
in equation 11.1 represent a population of durations made up of 16.7% (one-sixth)
optimistic ( T o ); 66
The weights assigned to these times (coefficients of T o ,
T m ,
.
7% (four-sixths) most
likely ( T m ); and 16.7% (one-sixth)
pessimistic ( T p ).
Several symbols are used in other textbooks to represent the mean (arithmetic
average), such as μ and X .
The standard deviation for the expected duration (σ e ) is
T p T o
6
σ e =
(11.2)
and the variance ( V e )is
V e e
(11.3)
Now, add the expected duration for all activities on the studied path ( T E ),
n
T E =
( T e ) i
(11.4)
i =1
The variance ( V E ) and standard deviation (σ E ) for the entire path are calculated as
n
e ) i
V E =
(11.5)
i =1
and
σ E = V E
(11.6)
With the information just calculated for the examined path, we can calculate the
probability that an event will occur on or by a certain date ( T S ) by using the normal
distribution formulas:
Z = T S T E
σ E
(11.7)
where Z (called the Z-function ) represents the number of standard deviations (σ E )
away from the mean ( T E ).
Search WWH ::




Custom Search