We compress each of these activities by 1 day to shorten the project duration
from 22 days to 21 days.
Cycle 4
Path
Duration (days)
ABEH
24
24
23
22
21
ACEH
25
24
23
22
20
ACFH
23
22
22
21
20
ACFG
24
23
23
22
21
ADG
23
23
23
22
21
Note that path ACEH was cut by 2 days because it contains both C and E.
Now the total cost has increased by $20 ($140 increase in direct costs and
$120 decrease in indirect costs). The next step is to find an alternative to
activity E because it is completely crashed. The next least-cost combination is
B, C, and D, at a total cost of $165. In this case, the total cost has increased
by $45.
Cycle 5
Path
Duration (days)
ABEH
24
24
23
22
21
20
ACEH
25
24
23
22
20
19
ACFH
23
22
22
21
20
19
ACFG
24
23
23
22
21
20
ADG
23
23
23
22
21
20
Note that the critical paths may change in every round. Now, activity C is
also completely crashed. Our next choice is the combination of B and G at a
combined cost of $225, with a net increase of $105 in the total cost.
Cycle 6
Path
Duration (days)
ABEH
24
24
23
22
21
20
19
ACEH
25
24
23
22
20
19
19
ACFH
23
22
22
21
20
19
19
ACFG
24
23
23
22
21
20
19
ADG
23
23
23
22
21
20
19
Activity B is now completely crashed. All paths are tied at 19 days. The
only remaining option is to combine activities G and H at a cost of $270, with
an increase of $150 in the total cost.
 