what it actually cost the contractor). This is called the earned value (EV), or
budgeted cost for work performed ( BCWP ).
However, the contractor's actual cost was $6,800. This is called actual
cost for work performed ( ACWP ).
Cost Variance ( CV )= BCWP ACWP = 6
,
400 6
,
800
=− $400
Schedule variance ( SV )= BCWP BCWS = 6
,
400 5
,
333
= $1
,
067
Schedule variance in days ( SV
,
days )= SV ( $ )∕ Daily planned budget
= $1
,
067 $266
.
67 = 4days
Cost performance index ( CPI )= BCWP ACWP = 6
,
400 6
,
800 = 0
.
94
Schedule performance index ( SPI )= BCWP BCWS = 6
,
400 5
,
333 = 1
.
20
Forecasted cost variance ( FCV )= CV ∕% Complete = $400 26
.
7 %
=− $1
,
500
Forecasted schedule variance ( FSV )= SV ∕% Complete = 4 26
.
7 %= 15 days
The results are tabulated as follows:
Activity
Doghouses
TOTALBUDGET($)
24,000
% COMPLETE
26.7
ACWP ($)
6,800
BCWP ($)
6,400
BCWS ($)
5,333
CV ($)
400
SV ($)
1,067
SV (DAYS)
4
CPI
0.94
SPI
1.20
FCV ($)
1,500
FSV (DAYS)
15
From simple observation, we can tell the following:
The project is 26.7% complete.
The project is ahead of schedule by 4 days (planned to finish 6.67 units
in 20 days but finished 8 units).
 