Civil Engineering Reference
In-Depth Information
2.
Cost/Budget:
Percent complete
=
Actual Cost
∕
Total budget
=
$560
∕
$3
9
%
complete
3.
Man-hours:
Percent complete
=
Actual man-hours
∕
Total man-hours
=
4
∕
13
=
30
,
120
=
17
.
8
%
complete
4.
Duration:
Percent complete
=
Actual duration
∕
Total duration
=
2 hours
∕
5 hours
=
40
%
complete
5.
Workday Unit (becomes here work-hour unit):
Percent complete
=
Actual Units
∕
Total Units
=
4
∕
7
=
57
%
complete
Methods 2 through 5 are calculated based on baseline (budget,
man-hours, duration). They are correct based on actual work only if
everything went as planned (on budget and on schedule).
Now, to make things a little more complicated, let's assume that
the hollow-core doors actually cost the contractor $230 and that each
one took an extra hour for installation (each). Also assume that the
expectation for the third activity did not change.
.
Actual cost for first two activities
=
230
+
3
∗
40
=
$350 each
At Completion-cost for project
=
2
∗
350
+
2
,
560
=
$3
,
260
At Completion man
−
hours for project
=
3
+
3
+
3
∗
3
=
15 man
−
hours
At Completion duration for project
=
3
+
3
=
6 hours
New percent complete estimates will emerge based on methods
2 through 5:
6.
Actual
Cost/Budget:
Percent complete
=
$700
∕
$3
,
260
=
21
.
5
%
complete
7.
Actual Man-Hours:
Percent complete
=
6
∕
15
=
40
%
complete
8.
Actual Duration:
Percent Complete
=
3
∕
6
=
50
%
complete
9.
Actual Work-hour Unit:
Percent complete
=
Actual units
∕
Total units
=
6
∕
9
=
66
.
7
%
complete
If this is not confusing enough, let's say that the foreman “believes” the
project is about 35% complete! These percentages can be rearranged as:
1. Units
%
Completed
=
2
∕
3
=
66
.
7
%
2. Cost % Complete:
Baseline
%
Complete
=
$560
∕
$3
,
120
=
17
.
9
%
Actual
%
Complete
=
$700
∕
$3
,
260
=
21
.
5
%
Search WWH ::
Custom Search