Civil Engineering Reference
In-Depth Information
example, a contractor is installing 25 doors. Four doors that have not yet been
started are 0% complete. Eight doors have had their frames erected. They are
considered 30% complete. Another six doors have been hung. They are said
to be 50% complete. Four more doors have been painted, making them 75%
complete. The last three doors have had the hardware installed. They are now
100% complete. Each door goes through the stages for installation, shown in
the following chart:
Task
Weight (%)
Cumulative Weight (%)
No. Units
% Complete Weight
Notyetstarted
0%
0%
4
4*0%/25 = 0.0
Erect door frame
30%
30%
8
8 * 30%/25 = 0.096
Hang door
20%
50%
6
6 * 50%/25 = 0.120
Paint door
25%
75%
4
4 * 75%/25 = 0.120
Install hardware
25%
100%
3
3 * 100%/25 = 0.120
25
Total = 0.456 = 45.6%
6. Weighted or equivalent units: The weighted or equivalent units method is used
for large and complicated activities that usually comprise several consecutive
or overlapping subactivities. The method involves the following five steps:
a. Assign a weight to each subactivity so that total weight = 100%.
b. Multiply the weight of each subactivity by the quantity of the total activity.
This is the “equivalent weight” in units for each subactivity.
c. Determine the percent complete for each subactivity by using one of the
previously discussed methods.
d. Multiply the percent complete for each subactivity by its equivalent weight.
The result is the “earned quantity.”
e. Add earned quantities for all activities and divide by total quantity.
This is the percent complete for the total activity. For example, for a
wall-framing activity, with a total quantity of 3.5 MBF (1,000 board-feet),
the information shown in the chart may be true:
Unit a
Assigned
Weight
Subactivity
Total
Quantity
Equivalent
MBF
Completed
Quantity
Earned
MBF
0.04
Bottom Plates
EA
20
0.14
20
0.14
0.40
Studs
EA
320
1.40
210
0.92
0.08
Corners
EA
12
0.28
8
0.19
0.12
Blocking
EA
160
0.42
92
0.24
0.14
Door Openings
EA
10
0.49
5
0.25
0.16
Window Openings
EA
12
0.56
5
0.23
0.06
Top Plates
EA
40
0.21
0
0.00
1.00
Total
MBF
3.50
1.97
a EA = each.
Percent complete = 197∕3
.
50 = 56
.
3%
 
Search WWH ::




Custom Search