Figure 7.13 Project update cycle
Design Development 90%
1-Sep-15
31-Dec-15
(a)
Design Development 90%
1-Oct-15
31-Dec-15
(b)
Design Development 90%
1-Oct-15
31-Jan-16
(c)
Figure 7.14 Design development: (a) 90% activity as originally planned; (b) 90% activity with
start delayed one month and finish date kept as planned; (c) 90% activity with start delayed
one month and original duration maintained
start was delayed 1 month (see Figure 7.14a). Unless the scheduler is told explicitly
by the project manager, there are two possibilities:
1. Keep the end date, 31 DEC 2015, which means the duration will shrink by 30
days (Figure 7.14b).
2. Keep the original duration, which means the end date will slip by 30 days to
30 JAN 2016 (Figure 7.14c).