Civil Engineering Reference
In-Depth Information
in Figure 6.7. Another scenario is shown in Figure 6.8 with the peak
use pushed to days 23 (9 laborers) and 24 (10 laborers) by delaying
activities E by 3 days, G by 6 days, and J and L by one day each. We
can still meet the original finish date, 28 days, with no delay.
9, 13
D
4
23, 27
16, 19
19, 23
K
4
E
3
23, 27
23, 26
19, 23
27, 28
24, 25
I
4
L
1
M
1
0, 6
A
6
6, 9
14, 19
9, 19
19, 23
B
3
C
10
F
5
26, 27
27, 28
19, 24
24, 26
9, 19
14, 19
0, 6
6, 9
H
5
J
2
16, 19
25, 27
20, 25
G
3
22, 25
Figure 6.5 Logic network solution for Example 6.3
c. Only 8 laborers available at any time . In this case, the project must be
delayed by 1 day (Figure 6.8). This is an example of forward resource lev-
eling , in which resources are not available to both satisfy the demand
for all activities and finish on time. This situation is discussed at the
end of this example.
d. Only 8 laborers available at any time but allow activities to be interrupted .
Even with interruptible activities, we could not satisfy the activities'
need for resources and maintain the total resource daily usage within
8 laborers, yet finish in 28 days. We need 29 days (Figure 6.9). In
Figure 6.10, we managed to do it in 28 days with one minor violation
of the logic: we allowed activity K to start one day before the completion
of activity I.
Search WWH ::




Custom Search