B (successor) can start after two days of work performed in activity A. Thus,
the first portion of A has to be at least two days. Similarly, the first portion of B
has to be at least three days. Note also that the two portions of A (A1 and A2)
can be done consecutively while the two portions of B (B1 and B2) cannot due
to the restrictions on B: First part has to start no later than day 2 so it will not
delay the start of C, and the second part cannot finish before A is completed.
2
3
0, 10
5, 12
2, 10
A
10
B
8
C
7
0, 10
2, 10
5, 12
Figure 5.29(c) Remedy 1: Network with elastic (stretchable) activities
0, 2
2, 5
5, 12
B1
3
C
7
A1
2
2, 10
7, 10
A2
8
0, 2
2, 5
B2
3
5, 12
4, 12
9, 12
Figure 5.29(d) Remedy 2: Network with split activities
2, 5
5, 12
0, 2
B1
3
C
7
A1
2
12
2, 7
7, 10
A2
5
2, 5
B2
3
0, 2
5, 12
PF
4, 9
7, 10
9, 12
12
A3
3
9, 12
Figure 5.29(e) Remedy 2: Network with Split Activities and only FS relationships
A1
A2
A3
B1
B2
C
123456789 0 1 2
s
Figure 5.29(f) Bar Chart for the networks in Figures 5.29 (d) and (e)