Environmental Engineering Reference
In-Depth Information
4
3
2
1
D = 1.2 m
L = 25 m
L = 50 m
L = 75 m
0
0
50
100
150
200
250
300
350
ickness of toe debris (mm)
Figure 14.10 The reliability of piles given toe debris of varying thickness.
updated reliability indexes for cases 1, 2, and 3 of different outcomes are 3.00, 2.72, and
3.50, respectively. Toe debris is found in case 2 but no remedial actions are taken; therefore,
the updated reliability is lower than other two cases. The reliability index for case 3 is the
highest among the three cases because the assumption that all piles would be tested and
repaired has been made for this case.
14.7 SuMMarY
It has been shown that pile tests, either load tests or integrity tests, are routinely conducted
during and after pile construction to ensure the safety of pile foundations and reduce costs.
Uncertainties in the key factors affecting the reliability of piles and the estimated reliability
4.0
3.5
3.0
2.5
2.0
D = 1.2 m, diffuse prior for p d
Prior b
Updated b, case 1
Updated b, case 2
Updated b, case 3
1.5
1.0
20
30
40
50
60
70
80
Pile length (m)
Figure 14.11 A comparison between updated and prior reliability indexes of piles using a diffuse prior for p d .
 
Search WWH ::




Custom Search