Environmental Engineering Reference
In-Depth Information
0.95
(a)
1.0
0.9
0.8
0.7
0.6
0.5
0.4
0.3
0.2
0.1
0
0.05
10
20
Consequence ($ MM)
Prior probability
(b)
1.0
0.9
0.8
0.7
0.6
0.5
0.4
0.6
0.3
0.2
0.1
0
0.1
10
20
Consequence ($ MM)
Likelihood function
(c)
1.0
0.9
0.8
0.7
0.6
0.5
0.4
0.76
0.24
0.3
0.2
0.1
0
10
20
Consequence ($ MM)
Updated probability
Figure 13.10 Illustrative example showing that uncertainty can increase with additional information.
likelihood function ( Figure 13.10b ) amplifies the probability of a $20 MM consequence,
reduces the probability of a $10 MM consequence, and produces an updated probability
distribution with more uncertainty in the consequence ( Figure 13.10c ).
The magnitude of uncertainty in a probability distribution is rationally and conveniently
measured with the theory of information entropy (e.g., Shannon 1948; Jaynes 1957; Tribus
1969):
[
] ×
Entropy of Information
=−
lnp c
()
pc
()
(13.8)
Ci
Ci
allc
i
 
Search WWH ::




Custom Search