Letter 46
To architect, on receipt of request for warranty
This letter is not suitable for use with MW, MWD or
GC/Works/1 (1998).
Dear
Thank you for your letter dated [
insert date
] issued as a notice under clause
7C/7D/7E [
substitute 7.5/7.6/7.7 when using IC or ICD and delete as appropriate
].
[
Add either:
]
However, we should point out that we are not required to provide such a
warranty/sub-contractor warranty [
delete as appropriate
] because the relevant
details were not inserted in part 2 of the contract particulars.
[
Or:
]
We are putting the necessary measures in place to provide the warranty as
requested.
Yours faithfully