Letter 290
To architect, if contractor instructed to carry out named person's work
after termination of named person's employment
This letter is only suitable for use with IC or ICD.
Dear
We are in receipt of your instructions under the provisions of Schedule 2,
paragraph 7.2 of the conditions of contract.
This clause permits us to sub-contract the [ insert nature of work ] work if we so
wish. We are giving the matter our urgent consideration and if we decide to so
sub-let, we will write to you again.
Yours faithfully
[ Note that a paragraph 7.2 instruction ranks as a clause 2.19 relevant event, a
clause 4.17 relevant matter and as a variation. ]