Letter 289
To architect, if employment of named person terminated under
ICSub/NAM/C clause 7.4, 7.5 or 7.6
This letter is only suitable for use with IC or ICD.
Dear
We refer to the termination of the [ insert nature of work ] sub-contract
employment of [ insert name ]on[ insert date ] under the provisions of
ICSub/NAM/C clause 7.4/7.5/7.6 [ delete as appropriate ]. In accordance with
the provisions of Schedule 2, paragraph 10.2 of the conditions of main contract,
we have taken reasonable action to recover additional amounts payable to us
by the employer as a result of the application of paragraph 8.1/8.2/9 [ delete
as appropriate and add, if appropriate: ] together with an amount equal to the
liquidated damages that would have been payable or allowable by us to the
employer under clause 2.23 of the main contract, but for the application of
Schedule 2, paragraph 8.1/8.2/9 [ delete as appropriate ]. The total of such
amounts is [ insert total ] made up as follows: [ insert a breakdown of the amount ].
[ Add either: ]
We attach copies of our letters of the [ insert dates ]to[ insert name ] which we
consider to be reasonable action.
[ continued ]