Letter 268
To sub-contractor, if sub-contractor has correctly sent 7 day notice of
intention to suspend performance of obligations
Dear
We are in receipt of your letter of the [ insert date ] which you have sent as a
notice in accordance with clause 4.11 [ substitute '4.13' when using ICSub/C,
ICSub/NAM/C or ICSub/D/C or '24' when using GC/Works/SC ] of the
sub-contract.
We regret that you have felt it necessary to send such a notice, but we are
pleased to enclose our cheque in the sum of [ insert amount ]. We hope you
will accept our apologies for this oversight.
Yours faithfully