Letter 263
To sub-contractor, giving withholding notice.
Dear
Take this as written notice in accordance with clause 4.10.3 [ substitute
'4.12.2' when using ICSub/C, ICSub/NAM/C or ICSub/D/C or '21.2.3' when using
GC/Works/SC ] that we propose to withhold the sum of [ insert amount ]fromthe
amount notified for payment on [ insert date ].
The grounds for withholding and the amount attributable to each ground are
as follows: [ list the grounds with the amount stated for each ground. The list should
be as detailed as possible ].
Yours faithfully