Letter 260
To sub-contractor, applying for payment of loss and/or expense (b)
This letter is only suitable for use with GC/Works/SC.
Dear
We hereby give notice and make application under clause 12.3 of the
sub-contract.
We have been caused direct expense because the regular progress of the Works
has been materially affected by the following circumstances [ describe ].
Particulars of the calculation of such direct expense are enclosed and we
should be pleased to have your agreement by close of business on [ insert date ]
to the amount of [ insert amount ].
In accordance with clause 12.3.3 we confirm that we are entitled to recover
expense under clause 12.3.
Yours faithfully