Letter 257
To sub-contractor, if sub-contract works not complete within the period
for completion (b)
This letter is only suitable for use with GC/Works/SC.
Dear
In accordance with clause 12.1 of the sub-contract, we hereby give notice that
the sub-contract [ insert nature of works ] works were not completed within the
period for completion/revised period for completion [ delete as appropriate ]
ending on [ insert date which should not be unreasonably earlier than the date of
this letter ].
You are in breach of the sub-contract and we draw your attention to
clause 12.2 and our right to recover from you the amount of any direct loss
and/or expense which we have suffered or incurred as a result of your failure
to complete in due time. We reserve all our rights and remedies.
Yours faithfully