Letter 253
To sub-contractor, fixing a new period for completion after practical
completion of the sub-contract works
This letter is not suitable for use with GC/Works/SC.
Dear
In accordance with clause 2.18.5 [
substitute '2.12.3' when using ICSub/C,
ICSub/NAM/C or ICSub/D/C
] and after reviewing all the evidence available
to us [
add, if appropriate: 'including previous extensions of time'
], we
[
Add:
]
hereby extend the sub-contract period by [
insert additional period
]. The revised
period for completion of the sub-contract works is now [
insert period
].
[
Or, when using SBCSub/C, SBCSub/D/C or DBSub/C:
]
hereby shorten the sub-contract period by [
insert the reduction
] having regard
to directions for relevant sub-contract omissions. The revised period for
completion of the sub-contract works is now [
insert period
].
[
Or:
]
hereby confirm the period for completion previously fixed, namely [
insert
period
].
Yours faithfully